Tasks:
  New construction under CPI contract.
Project Management.

- Tenant coordination mission.
- Areas were handed over to the tenants as cold shells - when fitting in the foreseen specifications, tenant works were undertaken by the contractor otherwise considered as additional works and subject to variations. Tenant delays and design stages were hard to be controlled. Overall completion was many times postponed.
- Monthly and Bimonthly reports in English.
     
 
Information:
References:
  Location
Date
Owner
Architect
Overall Area
Retail
Restaurants
Offices
Cinemas
Parking
Lille - Villeneuve d'Ascq
2008
Heron
Paindavoine Parmentier Architectes
45.000sqm
12.000sqm
5.600sqm
8.500sqm
12 screens - 2.850 seats
1.000 places